MACH Acoustics worked alongside
B3 Burgess Architects and developed one of the first schools to be cross
ventilated post the introduction of BB93.
The proposed veneration scheme is shown below, as can be seen to this
drawing two rows of classroom block were located either side of a large
teaching atrium.
The
proposed detail on the first floor was to place the attenuators at and angel
following the roof line. As in the case
of London and West London
Academies, the attenuators were placed over cupboards. The ground floor detail was made simpler
since a flat slab was available. The design
of the attenuator was boosted by the fact that the air could also pass through a
relatively large service void, which further enhanced the acoustics performance
of the ventilator.
No comments:
Post a Comment